Tunnel Escape Pipe Installation:

1. The pipes used for the escape passage can be steel pipes with a diameter of φ600 to φ800mm and a wall thickness of no less than 6mm, with a recommended length of 5m per section.

2. The starting point of the escape passage should be at the newly constructed arch closure at the loop end, with a distance from the face not exceeding 20m. A working rope should be reserved inside the pipe to facilitate escape in case of emergencies.

3. The escape pipes are connected using flange connections.

4. Each division and tunnel team should promptly purchase materials and actively organize the installation of pipes upon receiving this notice, while also formulating specific implementation methods and promotion plans based on their actual conditions to ensure the orderly installation of the rescue pipes and the construction of the tunnel.

Luo Yang Guo Run New Material Technology Co., Ltd. specializes in: escape pipes, tunnel escape pipes, highway tunnel escape pipes, new impact-resistant tunnel escape pipes. Direct shipping from the manufacturer at low prices. Welcome both new and old customers to visit and inspect.

Performance of Tunnel Escape Pipes:

1. The highway tunnel escape pipes and new impact-resistant escape pipes have good corrosion resistance and impact resistance even under low-temperature conditions.

2. Made with our company's unique formula, the highway tunnel escape pipes and new impact-resistant escape pipes have high corrosion reliability.

3. Reasonably designed and easy to install. The pipe ends are equipped with connection components and lifting rings to ensure easy installation and lifting.

4. Low material costs save procurement costs for engineering projects.

5. The highway tunnel escape pipes and new impact-resistant escape pipes have strong corrosion resistance, are easy to construct, and have a service life of 30-50 years.

6. The bottom layer of the tunnel construction escape pipe contacts with the steel pipe surface is coated with epoxy powder corrosion-resistant coating, and the outer layer is resin anti-rust paint. The inner wall is smooth, allowing for quick escape during incidents, minimizing secondary injuries.

7. Our highway tunnel escape pipes and new impact-resistant escape pipes are recognized for their effective use and performance of the pipe corrosion-resistant coating, and have been applied in many projects.

Layout Requirements for Tunnel Escape Pipe Lines:

1. During the movement and positioning of the secondary lining carriage, the escape pipes should be disassembled section by section temporarily; it is strictly forbidden to dismantle all at once to ensure the functionality of the escape pipes at all times.

2. When the highway tunnel escape pipes and new impact-resistant escape pipes pass through the excavation steps, they should be arranged according to the steps and installed with 135° transition joints, ensuring that the escape pipes are level, dry, and smooth, and must not be used for purposes other than emergency escape.

3. The length of the highway tunnel escape pipes and new impact-resistant escape pipes should be 100m.

4. The pipes used for the escape passage should be φ800mm steel pipes or other impact-resistant pipe materials. The length of each pipe section should be 15m, with a wall thickness of 7mm. Connections between pipe sections can use casing with a diameter greater than that of the escape pipe, with each end connected by 1m and temporarily fixed with rubber rings or wooden wedges. To ensure the pipes can withstand the pressure from collapse materials, the material used for the pipes must ensure pressure-bearing capacity and the firmness of the joints, and must be tested in a laboratory before being used in the tunnel.

5. The construction site should prepare sufficient pipes and connection materials based on the surrounding rock conditions and excavation methods of the tunnel. In addition to whole pipe sections, short pipe sections of 1m, 2m, and 3m should also be prepared.

6. Highway tunnel escape pipes and new impact-resistant escape pipes should be processed according to the material and actual site conditions, ensuring simple, firm, and reliable connections. Temporary fixing measures should be implemented on the ground, and temporary sealing caps can be added to the pipe openings during construction, making them easy to open and close.

7. Highway tunnel escape pipes and new impact-resistant escape pipes should use φ800mm steel pipes or other impact-resistant pipe materials. The starting point should be at the constructed secondary lining end, with a distance from the secondary lining end not exceeding 5m, laid from the lining working face to an appropriate position within 20m of the excavation face. The pipes should be laid along one side of the initial support towards the face, with a working rope reserved inside for easy escape, rescue, communication, and the transmission of various items. Longitudinal connections of steel pipes can use chains or similar measures to prevent the pipes from being dislodged during a collapse.

Tunnel Pipe Engineering Cases:

China Communications Second Engineering Bureau Fourth Company   Φ800 highway tunnel escape pipes, new impact-resistant escape pipes 200 meters

Yunnan Xiangli Expressway Second Project Department   Φ800 tunnel escape pipes 300 meters

China Communications Second Navigation Engineering Bureau Co., Ltd.   Φ800 tunnel escape pipes 70 meters

China Communications Second Public Bureau Liupanshui Weining Expressway    Φ800 highway tunnel escape pipes 500 meters

Yunnan Second Highway Bridge Co., Ltd.   Φ800 tunnel escape pipes 150 meters

Yunnan Second Highway Bridge Engineering Co., Ltd.   Φ800 tunnel escape pipes 80 meters

China Water Resources and Hydropower Eleventh Bureau   Φ800 highway tunnel escape pipes 75 meters

China Railway Tunnel Bureau Ningbo Ninghai Expressway   Φ800 tunnel escape pipes 400 meters

China Railway Fourteenth Bureau Yulin Expressway   Φ800 highway tunnel escape pipes, new impact-resistant escape pipes 300 meters

China Railway Sixth Bureau Group Shijiazhuang Railway Construction Co., Ltd.   Φ800 tunnel escape pipes 250 meters

 

Luo Yang Guo Run New Material Technology Co., Ltd. welcomes you to visit our factory!

Sales Manager: Manager Sun 13698887149

Fax: 0379-65227507  Business QQ: 2021704852

Factory Address: China.Luoyang Airport Industrial Cluster Area. Zhejiang Merchant Industrial Park

```
Product Consultation
Supplier
LuoYang Guorun New Materials Technology Co., Ltd.
location
HenanProvince
About Us
```plaintext Luyang Guorun New Materials Technology Co., Ltd. is a technology enterprise integrating research, development, production, and sales. It specializes in producing a wide range of pipe materials and fittings, including ultra-high molecular weight polyethylene (UHMW-PE) pipes, UHMW-PE composite pipes, HDPE steel-reinforced corrugated pipes, HDPE pipes, municipal sewage pipes, lined rubber pipes, desulfurization pipes, and other series products. The company also has the capability for designing, measuring, and installing pipeline projects. Luyang Guorun New Materials Technology Co., Ltd. is a specialized manufacturer of wear-resistant UHMW-PE pipes, wear-resistant high-pressure pipes, wear-resistant elbows, tailings pipes, lined rubber steel pipes, corrosion-resistant lined rubber pipes, desulfurization pipes, plastic pipe floats, dredging pipes, dredging pipelines, steel-lined plastic pipes, steel-lined PTFE pipes, etc. Over the years, the company has been dedicated to serving industries such as mining, power, metallurgy, dredging, chemical engineering, environmental protection, and more. Its products are used in mining conveyance, river dredging projects, chemical plant process pipelines, high-temperature, strongly corrosive medium transportation, industrial water conveyance, and anti-corrosion pipelines. Products have been utilized by over 600 customers across more than 30 provinces and cities nationwide. The rich corporate heritage has positioned Guorun Pipe Industry at the forefront of its industry since its inception. The company's production facility is located in the Luoyang Airport Industrial Park, covering an area of over 100 mu with more than 20,000 square meters of factory space. The company maintains a long-term and stable partnership with Shanghai research institutions and is the test base of the Shanghai Chemical Research Institute. In providing quality products and services to customers, the company has established strategic partnerships with groups such as Australia's Nanot Group, Japan's Prince Group, and Germany's KCH Group. The company continuously develops new products, including wear-resistant and corrosion-resistant coatings for equipment such as tanks, reactors, and vessels. The company has established a complete system from product design, processing, installation, commissioning, to after-sales service. Luyang Guorun New Materials Technology Co., Ltd. currently produces UHMW-PE pipes ranging from Φ63mm to Φ1000mm with wall thicknesses of 7 to 35 mm and working pressures from 1 to 3 MPa. Pipes with working pressures above 2 to 3 MPa can also use UHMW-PE composite pipes. The company’s products have been listed among the top 500 major scientific and technological achievements by the China Industrial Association and recognized as environmentally friendly products by the U.S. Environmental Technology Import and Export Committee. These products are used in various applications such as mine slurry transportation, coal industry water-coal slurry, power plant fly ash, chemical water transportation, chemical industry corrosive media, crude oil, natural gas transportation, salt chemistry in lakes and seas, river dredging, etc. Our high-caliber sales team, professional technical solutions, mature modern management systems, comprehensive product production, inspection, installation, commissioning, and after-sales service systems all reflect the excellence of our products and services. We warmly welcome your visit and look forward to serving you! ```